When a dry air cooler is pushed beyond its original design duty, two familiar retrofits have already been examined: adding spray to the tube bundle, and humidifying the intake air. This article presents a third option — integrating a water cooler in series or in parallel — for plants where the air cooler platform simply has no spare footprint.
Where no additional space is available on the air cooler platform, the cooling demand created by a capacity upgrade can still be satisfied by arranging water coolers either in parallel or in series. Figure 1 shows a series arrangement: everything outside the red frame is the original production and operating system, while everything inside the red frame is the newly added water cooler and its associated heat exchange equipment.
Overhead vapour from the distillation column is fully or partially condensed in the dry air cooler. By regulating pressure and temperature at the air cooler, the temperature of the stream entering the reflux drum can be controlled, which prevents cavitation in downstream rotating equipment and avoids excessive column pressure.
If, in actual operation, the material leaving the air cooler is warmer than the design value, the water cooler provides a second cooling stage so that the stream meets the needs of downstream production.
| Approach | Working Principle | Key Constraint |
|---|---|---|
| 1. Tube bundle spray | Water film on the bundle surface raises heat rejection | Water supply, scaling and bundle corrosion control |
| 2. Intake air humidification | Lower dry-bulb inlet air temperature increases available temperature difference | Climate dependent; humidification equipment and water quality required |
| 3. Series / parallel water cooler | An additional water-cooled exchanger stage downstream of the air cooler | Needs an extra cooling source and available plot area for the cooling tower |
As shown in Figure 2, adding a water cooler effectively raises the achievable duty. The water cooler, however, must be backed by matching cooling equipment that supplies its duty. That cooling demand can be met either from the original refrigeration system or from a newly added cooling tower.
Supplying the extra duty from the existing refrigeration system increases its load and may leave the original refrigeration capacity unable to cover the upgraded production rate. This option should therefore be considered only where a generous refrigeration margin already exists. In most cases a new cooling tower is required to serve the heat exchange demand of the water cooler.
A cooling tower rejects heat from the internal circulating water to dry ambient air; the inlet-to-outlet water temperature difference is normally held at around 10 °C.
| Check Item | What to Verify |
|---|---|
| Available plot area | Space for cooling tower, water cooler and interconnecting piping |
| Refrigeration margin | Confirm whether existing refrigeration can absorb the additional duty |
| Water temperature approach | Circulating water temperature difference of about 10 °C across the cooling tower |
| Pipe material | Compatibility with both process material and cooling water |
| Water quality monitoring | pH meter and other instruments in the circulating water loop |
| System pressure drop | Reflux drum pressure and reflux pump NPSH after the water cooler |
Series or parallel water coolers give revamp engineers a practical third lever for lifting dry air cooler duty when platform space is exhausted and climate-based measures are insufficient. The concept is simple, but its success depends on disciplined design: securing a reliable cooling source, confirming the refrigeration margin, selecting compatible materials, monitoring water quality and keeping the pressure profile at the reflux drum safely above the cavitation limit.
![]()
![]()
When a dry air cooler is pushed beyond its original design duty, two familiar retrofits have already been examined: adding spray to the tube bundle, and humidifying the intake air. This article presents a third option — integrating a water cooler in series or in parallel — for plants where the air cooler platform simply has no spare footprint.
Where no additional space is available on the air cooler platform, the cooling demand created by a capacity upgrade can still be satisfied by arranging water coolers either in parallel or in series. Figure 1 shows a series arrangement: everything outside the red frame is the original production and operating system, while everything inside the red frame is the newly added water cooler and its associated heat exchange equipment.
Overhead vapour from the distillation column is fully or partially condensed in the dry air cooler. By regulating pressure and temperature at the air cooler, the temperature of the stream entering the reflux drum can be controlled, which prevents cavitation in downstream rotating equipment and avoids excessive column pressure.
If, in actual operation, the material leaving the air cooler is warmer than the design value, the water cooler provides a second cooling stage so that the stream meets the needs of downstream production.
| Approach | Working Principle | Key Constraint |
|---|---|---|
| 1. Tube bundle spray | Water film on the bundle surface raises heat rejection | Water supply, scaling and bundle corrosion control |
| 2. Intake air humidification | Lower dry-bulb inlet air temperature increases available temperature difference | Climate dependent; humidification equipment and water quality required |
| 3. Series / parallel water cooler | An additional water-cooled exchanger stage downstream of the air cooler | Needs an extra cooling source and available plot area for the cooling tower |
As shown in Figure 2, adding a water cooler effectively raises the achievable duty. The water cooler, however, must be backed by matching cooling equipment that supplies its duty. That cooling demand can be met either from the original refrigeration system or from a newly added cooling tower.
Supplying the extra duty from the existing refrigeration system increases its load and may leave the original refrigeration capacity unable to cover the upgraded production rate. This option should therefore be considered only where a generous refrigeration margin already exists. In most cases a new cooling tower is required to serve the heat exchange demand of the water cooler.
A cooling tower rejects heat from the internal circulating water to dry ambient air; the inlet-to-outlet water temperature difference is normally held at around 10 °C.
| Check Item | What to Verify |
|---|---|
| Available plot area | Space for cooling tower, water cooler and interconnecting piping |
| Refrigeration margin | Confirm whether existing refrigeration can absorb the additional duty |
| Water temperature approach | Circulating water temperature difference of about 10 °C across the cooling tower |
| Pipe material | Compatibility with both process material and cooling water |
| Water quality monitoring | pH meter and other instruments in the circulating water loop |
| System pressure drop | Reflux drum pressure and reflux pump NPSH after the water cooler |
Series or parallel water coolers give revamp engineers a practical third lever for lifting dry air cooler duty when platform space is exhausted and climate-based measures are insufficient. The concept is simple, but its success depends on disciplined design: securing a reliable cooling source, confirming the refrigeration margin, selecting compatible materials, monitoring water quality and keeping the pressure profile at the reflux drum safely above the cavitation limit.
![]()
![]()